Buleleng Lawmakers Inspect Singaraja Drainage Project at 27 Percent

Drainage and streetscape work around Pasar Anyar in Singaraja was 27 percent complete when Buleleng lawmakers inspected it on Oct. 12. The project is scheduled to finish Dec. 17, 2026.

By

Editor: Mursyid Sonsang

· 2 min read

Open the larger photo. Illustration: Large weathered concrete drainage rings piled outdoors with overgrown dry weeds.
Illustration: Large weathered concrete drainage rings piled outdoors with overgrown dry weeds. · Photo: Theodore Nguyen / Pexels

Singaraja — Construction of drainage and streetscape improvements on Jalan Diponegoro, around Pasar Anyar, had reached 27 percent when Commission II and Commission III of the Buleleng Regional House of Representatives inspected the project on Oct. 12, 2026.

The work is intended to improve water flow and reduce the risk of standing water and flooding in the market area. Lawmakers said the existing drainage system needs technical evaluation so the new channels are connected and function properly after construction.

Why it matters for Singaraja’s market district

For traders, road users and nearby residents, the project is meant to address a practical problem: water that does not drain efficiently around Pasar Anyar. The inspection also identified obstacles that could affect implementation, including vehicle parking, traders operating near the site and the condition of the old drainage channels.

The project is being carried out by CV Cadudasa Pratama under the supervision of CV Manca Geni. Its contract value is IDR 4,749,733,000 (about US$300,000). Work began on Aug. 28, 2026, and is scheduled to continue for 120 calendar days, ending on Dec. 17, 2026.

The broader arrangement of Jalan Diponegoro includes the Pasar Anyar area and is intended to benefit traders, road users and the surrounding community. Earlier plans for the area also included improvements to pedestrian facilities and parking, with completion targeted for December 2026.

Buleleng lawmakers urged the contractor, supervising consultant and relevant local agencies to coordinate more closely so technical problems do not delay completion. They also stressed that the drainage must be assessed as a connected system, rather than treated only as a surface-improvement project.

The project’s next stated milestone is completion by Dec. 17, 2026, in line with the contract. The scheduled deadline gives the contractor and supervising parties a clear date for finishing the drainage and streetscape work around the market district.

Sources

Read next

  1. More on this story

  2. Most read in Environment

  3. Today’s top story

Related

‹ Back to the home page

Share this story

Share as an image

For an Instagram Story, a WhatsApp Status or TikTok. The story link is copied too, ready to paste into the Link sticker.

Preview of the Story / Status card for this story
Story / Status · 9:16
Save image
Preview of the Feed card for this story
Feed · 4:5
Save image

Reading tools

Normal

A sample of the body text size. Your choice is kept on this device.